Project Costs and Funding

North London Waste Authority (NLWA) is responsible for the cost-effective disposal of waste collected by the seven north London boroughs of Barnet, Camden, Enfield, Hackney, Haringey, Islington and Waltham Forest.

The Energy Recovery Facility (ERF) remains the best value solution for managing north London's non-recyclable waste while delivering improved environmental and social outcomes. A comprehensive value for money assessment, undertaken in line with HM Treasury's Green Book guidance, concluded that alternative waste disposal options would be more expensive over the long term.

In January 2022, NLWA contracted ACCIONA to design and build the Energy Recovery Facility. Most risks were transferred to the contractor but a number of risks remained with NLWA. Members authorised an overall financial limit of £885 million, then considered sufficient to cover the Authority’s retained risks. Costs started to exceed expectations, with disputes over responsibility for increases, particularly those linked to site labour productivity. These disputes added legal costs and delivery uncertainty, leaving the Authority facing a significantly higher final contract price.

In 2026, following a detailed audit, options appraisal and negotiations, NLWA and ACCIONA agreed a contract amendment reflecting market conditions, project risks, inflation and the delivery programme. The £1,250 million lump-sum price, agreed after extensive negotiations and scrutiny by the Authority and its advisers, settles all disputes and transfers future labour risks to ACCIONA. The amendment aims to improve cost and delivery certainty, manage remaining risks and support completion of a publicly owned facility serving north London for decades.

Inflation and cost risks continue to be actively managed through the contractual arrangements in place with ACCIONA. As the project progresses and key construction packages are completed, many cost risks reduce over time. NLWA maintains robust oversight of project costs and performance to protect the interests of residents and ensure the best available outcome for north London Borough's waste disposal.

The disposal of north London's waste is funded through a levy and charges paid by the seven constituent boroughs to NLWA. The cost of the Energy Recovery Facility will be met through this established funding mechanism, and boroughs have incorporated future levy requirements into their long-term financial planning. The cost per resident to dispose of waste is approximately £1 per week currently and will be about £1.50 when the new Energy Recovery Facility becomes operational.  

Delivering the Energy Recovery Facility provides a cost-effective and resilient long-term solution for managing north London's waste. As a publicly owned asset, the facility will reduce reliance on external waste disposal providers and exposure to market fluctuations, helping to provide greater certainty over future waste management costs. The cost per tonne of waste treated is expected to remain competitive when compared with alternative long-term disposal options available in the market.

NLWA is committed to securing the most cost-effective funding arrangements for the project. As a public authority, it can access borrowing from sources such as the Public Works Loan Board, enabling it to secure finance at rates that are generally lower than those available to private sector organisations and helping to minimise costs to council taxpayers.