Where is the project currently?

North London Waste Authority’s (NLWA) application for a Development Consent Order to build a new energy recovery facility, and associated development, was accepted for examination by the Planning Inspectorate (PINS) on 11 November 2015. You can view the application documents for the project in our Document Library.

On 24 February the Secretary of State for Business, Energy and Industrial Strategy granted a Development Consent Order for this project.

The construction preparation work is expected to start in 2019. The proposed construction programme is as follows:   

Timeline